MFG - Scheduling - Validation message has to be displayed if there is no enough days defined in production calendar to schedule work orders for a line

Issue No: MFG-616
Created 8/31/2015 10:43:47 AM
Type Bug
Priority Major
Status Closed
Resolution Fixed
Fixed Version 15.4
Description {panel:title=BRIEF:|bgColor=#E0EFFF} Validation message has to be displayed if there is no enough days defined in production calendar to schedule work orders for a line     {panel} {panel:title=STEPS AND RESULTS:|bgColor=#EAE6FF} Precondition : Do not configure production calendar for the line   # Create a WO and try to schedule it for the line ----* ACTUAL RESULT: System is rolling back the changes * EXPECTED RESULT: Validation message has to be displayed   {panel} {panel:title=SCREENSHOT / FAULT DETAILS:|bgColor=#EAE6FF}     {panel} {panel:title=ADDITIONAL INFO:|bgColor=#E0EFFF}     {panel}