MFG - Scheduling - System is not considering earliest start date while scheduling work orders

Issue No: MFG-589
Created 8/27/2015 4:07:45 AM
Type Bug
Priority Major
Status Closed
Resolution Fixed
Fixed Version 15.4
Description {panel:title=BRIEF:|bgColor=#E0EFFF} System is not considering earliest start date while scheduling work orders     {panel} {panel:title=STEPS AND RESULTS:|bgColor=#EAE6FF} # Go to work order schedule # Open any schedule and provide "earliest start date" for any WO # Click on reschedule ----* ACTUAL RESULT: System is not considering earliest start date while generating start date and end date * EXPECTED RESULT: Scheduled start date should be equal to or greater than earliest start date.   {panel} {panel:title=SCREENSHOT / FAULT DETAILS:|bgColor=#EAE6FF}     {panel} {panel:title=ADDITIONAL INFO:|bgColor=#E0EFFF}     {panel}