Description |
The load based contract, went in the logistics to schedule loads manually. The qty pulled from the contract is showing 1 ton where as the contract has 200 ton on the contract. Manually tried to change the qty but it wont allow to change.
Steps to reproduced:
# *The Load based contract# 10051 has 400 Tons, each load of 200 Tons*
!pastedImage_d104704_0.png!
# *Logistics, new load/shipment scheduling- enter transaction type, source type- contract, transport mode, and in the sequence area select the load based contarct # 10051. The quantity pulled in is 1 ton, wont let me manually change it to the contracted qty*
!pastedImage_d104704_1.png!
*
|