Description |
*This issue relates to i21 Help Desk ticket:* [ HDTN-274243 - Leadtime I21 - after slicing|https://helpdesk.irely.com/iRelyi21live/#/HD/Ticket/?ticket=HDTN-274243]
Customer has reported the below issue in their Live environment
Steps:
* Open the contract 1005346.472
* Slice the contract to 2 sequences
* For sequence 1 in the Vessel tab add the Loading port, Destination port, Sub Location, Storage location
* For sequence 2 in the Vessel tab add the Loading port, Destination port, Sub Location, Storage location
* Save the contract
Issue:
For sequence 2 the Planned Availability date is showing wrongly as 16/12/2022 calculating based on the sequence start date and the number of days configured in the Contract Positions for each position.
While It should be calculated as
Planned Availability date = Seq. start date + Lead time between Loading Port and Destination Port
+ Lead time at loading port + Lead time at destination port
= 1/11/2022 + 44 + 21 + 14
= 19/01/2023
The same issues has happened in other contracts also like 1005346.473, 1005415.2203, 1005415.2204
Acceptance:
It should calculate and display the Planned Availability date correctly in the contract
|