Description |
*This issue relates to i21 Help Desk ticket:* [ HDTN-263604 - Contract Start Date and End Date are not updated after slicing it|https://helpdesk.irely.com/iRelyi21live/#/HD/Ticket/?ticket=HDTN-263604]
Steps
1. Create a contract with a sequence.
2. Save the contract.
3. Select the contract sequence and Click on Slice.
!pastedImage_d167619_0.png|height=213,width=563!
4. Enter 350 in the sequence Quantity column and Click on Weekly.
!pastedImage_d167619_1.png|height=294,width=556!
5. Click on Slice
Issue:
System is not updating Contract sequence's start date and end date for the contract seq no 1.
!pastedImage_d167619_2.png|height=342,width=359!
Expectation
It should be based on user entered it in the slice window.
|