*{color:#ff0000}ERROR: Quantity changed automatically in error once selected the sales contract number to the sales order. {color}*
Created a Sales priced contract with 2 sequences for 500 bushels and 1000 bushels, both priced differently. Created a Sales order that has more bushels than the existing contract sequience 1 but less than the total amount (quantity) of the contract.
Steps followed:
# *Created a sales priced contract#12, for * Bruce Hoctor, WASCO SEED PLANT location, 1500 bushels. Sequence 1 for 500bushels, priced at $10 and sequence 2 for 1000bushels, priced at $8. *
* !pastedImage_d103607_0.png! *
**
# *Created a Sales order# SO-18, same entity and location. Enter PO number and selected the existing sales contract#12. Re-selecting of contract numer and sequence number is required [Jira ticket already entered for the contract number being wiped out after selecting the contract number and sequence number in the sequence area of sales order]. *
*Below images:*
*(A) Shows contract#12 selected with sequence 1, quantity shows 500 bushels*
* !pastedImage_d103607_1.png! *
**
*(B) Shows the contract number changed to 9 from 12 automatically once the quantity was edited to 800 bushels from 500 [Jira ticket already entered]*
* !pastedImage_d103607_2.png!*
# *Edited the contract number to 12 manually, and {color:#ff0000}the quantity changed to 899.80 automatically{color}. The original contract#12 does not have 899.80 bushels in the sequence 1 or 2. *