Steps:
1. Create new purchase contract where pricing type is Basis. Sample below:
!pastedImage_d114951_0.png!
2. Create Settlement Price for the item's commodity.
!pastedImage_d114951_1.png!
3. Create Basis Entry for the basis purchase contract.
!pastedImage_d114951_2.png!
4. Create another purchase contract where pricing type is Priced.
!pastedImage_d114951_3.png!
5. Price the basis purchase contract and save.
!pastedImage_d114951_4.png!
6. Create Load In ticket and select the purchase basis contract. On Manual Distribution screen, allocate the quantity on the 2 contracts and process. (Contract 1 = 13,964.314471 and Contract 2 = 4496.77)
!pastedImage_d114951_5.png!
7. It creates single Inventory Receipt. Order Qty, Receipt Qty and Cost are correct.
!pastedImage_d114951_6.png!
8. Open the voucher created
Issue:
Ordered Qty is incorrect for the basis purchase contract line item
!pastedImage_d114951_7.png!
Acceptance:
Should be the basis purchase contract quantity which is 170000
|